OTAKAR.AI
Rack power draw is set by GPU count and generation, not by the building. A GB200 NVL72 packs 72 GPUs and 36 CPUs into a single liquid-cooled rack; the next generation multiplies that further.
Think of it as swapping a household appliance for a small industrial furnace, and putting dozens of them in one room. The building didn't get bigger — the thing inside it got radically denser.
| Rack type | Power per rack | Cooling required |
|---|---|---|
| Traditional enterprise rack | 7–10 kW | Air |
| NVIDIA H100 (8-GPU servers) | 40–50 kW | Air / hybrid |
| NVIDIA H200 (8-GPU servers) | 50–70 kW | Liquid-assisted |
| NVIDIA GB200 NVL72 | 120–140 kW | Direct-to-chip liquid |
| Vera Rubin NVL144 (targeted, 2026–27) | up to 600 kW | Liquid, required |
| OCP 2025 concept racks | up to 1 MW | Liquid, required |
Power Usage Effectiveness is total facility energy divided by the energy that actually reaches IT equipment. A PUE of 1.0 is theoretical; a PUE of 1.5 means the building spends an extra 50% of IT load on cooling, distribution loss, and overhead.
PUE is the tax the building itself charges on top of the compute you actually wanted. Every tenth of a point above 1.0 is pure overhead — power spent moving and removing heat rather than running GPUs.
| Facility class | Typical PUE |
|---|---|
| U.S. average, 12-month trailing | ~1.4 |
| Typical enterprise facility | 1.5–1.6 |
| New-build target (industry benchmark) | ≤1.2 |
| Leading hyperscale (Google fleet-wide) | 1.09 |
| Best individual sites (Dublin, Eemshaven) | 1.07–1.08 |
Water Usage Effectiveness measures liters of water consumed per kWh of IT energy. Evaporative cooling towers trade electricity for water; closed-loop liquid and immersion cooling trade water for capital and complexity.
PUE and WUE pull in opposite directions. A facility can post an excellent power number by evaporating enormous amounts of water — the efficiency didn't disappear, it just moved from the electric meter to the water main.
| Cooling method | WUE (L/kWh) | PUE |
|---|---|---|
| Air cooling | ~0 | 1.4–1.8 |
| Evaporative cooling | 1.5–2.5 | 1.1–1.3 |
| Liquid / direct-to-chip | near 0 | 1.05–1.2 |
Construction cost is quoted per MW of IT capacity, not per square foot. Shell-and-core cost has risen from $7.7M/MW in 2020 to roughly $11.3M/MW in 2026 — before AI-specific fit-out.
The building is almost the cheap part now. What you're really pricing is transformers, switchgear, and liquid-cooling plumbing — the industrial guts, not the walls and roof.
| Market | Shell-and-core, $/MW |
|---|---|
| Low-cost U.S. (Texas, Ohio, Nevada) | $8M |
| Global average, 2026 | $11.3M |
| Northern Virginia, Silicon Valley | $14–18M |
| Tokyo, Singapore (priciest markets) | ~$15M |
| All-in AI build (incl. GPU fit-out) | $30–40M |
Power infrastructure — switchgear, transformers, medium-voltage cable, UPS, and interconnection — typically consumes 40–50% of total construction cost, more than the building envelope itself.
You are not really building a data center. You are building a substation with a very expensive computer room attached to it.
| Cost component | Range, $/MW |
|---|---|
| Shell and core | $3–5M |
| Mechanical / cooling systems | $2–4M |
| Electrical / power distribution | $3–5M |
| Fire suppression and controls | $0.5–1M |
| Land, interconnection, permitting (separate) | $1–10M+ |
Illustrative at PUE 1.5, a common facility average; a leading-edge liquid-cooled site (PUE 1.1) shrinks the cooling and loss bars substantially.
FERC targets 8–11 months for a generation project to clear the interconnection queue. Actual timelines in high-demand zones run 36–84 months — longer than the 12–24 months it takes to build the data center itself.
You can pour concrete and stack racks faster than you can get permission to plug them in. The constraint has flipped from "can we build it" to "can we get power to it."
| Grid / region | Queue or wait |
|---|---|
| FERC target (generation interconnection) | 8–11 months |
| PJM Interconnection, average | ~40 months |
| Active data-center load zones, U.S. | 36–48 months |
| National U.S. queue (all fuels) | 2.2–2.6 TW waiting |
| ERCOT (Texas) large-load queue | 410 GW; 87% data centers |
| New 50 MW site, London / Amsterdam | ~8–10 years |
Faced with multi-year grid delays, developers increasingly build generation "behind the meter" — on-site, bypassing the interconnection queue entirely. Over 130 GW of behind-the-meter capacity has been proposed for U.S. data center projects.
If the utility can't connect you in time, you become your own utility. It costs more per megawatt-hour, but "more expensive and on time" beats "cheaper and four years late."
| Technology | Deployment time |
|---|---|
| Fuel cells | ~90 days |
| Gas turbines (heavy-duty) | 3–7 years |
Because AI racks draw an order of magnitude more power each, a fixed number of megawatts now fits into far fewer racks — and a much smaller building footprint per megawatt.
Data centers aren't getting bigger buildings — they're getting smaller, denser ones that draw vastly more power per square foot than anything built a decade ago.
| Facility type | Racks for 100 MW | Sq ft per rack |
|---|---|---|
| Legacy enterprise (8 kW/rack) | ~12,500 | 25–30 |
| GB200 NVL72 (120–140 kW/rack) | ~700–800 | 30–50 |
The five largest hyperscalers are projected to spend $745–775B in capex in 2026 alone. Roughly 100 GW of new data center capacity is projected between 2026 and 2030 — doubling today's installed global base.
This is being described as the largest five-year surge to the U.S. grid since the 1980s. The AI buildout is now, functionally, an electricity infrastructure project that happens to run models.
| Metric | Value |
|---|---|
| Top-5 hyperscaler 2026 capex | $745–775B |
| New global capacity, 2026–2030 | ~100 GW |
| U.S. data centers, share of electricity (2024) | ~4% |
| U.S. data centers, projected share (2028) | 7–12% |
It depends on rack density, PUE, WUE, market-specific $/MW, interconnection timeline, and whether power is grid-sourced or built behind the meter.
Source note: figures are drawn from industry and analyst reporting (JLL, BloombergNEF, Carbon Direct, NREL, hyperscaler sustainability disclosures, and infrastructure trade press) current as of 2026. Individual facilities vary substantially by market, cooling architecture, and disclosure practice.